Ram’s 1 day work = 1/10
Shyam’s 1 day work = 1/20
(Ram’s + Shyam’s) 1 day work = 1/10 + 1/20
= (2 +1)/20
= 3/20
They will work together to complete the same work in 6 2/3 days.
Answer: They will work together to complete the same work in 6 2/3 days.